MWS FPSO Conversion for ENI Angola Block 15/6 East Hub Development Project

 

Client: Bumi Armada  
Timeline: 2014 - 2016

Marine Warranty Services for this project involves modules installation onto FPSO which were all done in Keppel Shipyard in Singapore. This will be transported to Offshore Angola where Mooring Offshore Installation and FPSO Hook will take place. This project is headed by the C&E Manager Mr. Francis Yang who works as the Project Manager for this job.

Our qualified engineers took part to witness all the attendances from weighing up to the installation of more than 40 modules onto the FPSO, all of which were done in Keppel Shipyard - Singapore. 

Phase 1 of the project which is the installation of mooring chain and suction pile has just been completed in Offshore Angola in preparation of the Phase 2 of the project which is the hook up of the FPSO at Angola Block 15/06 East Hub Field Development. The FPSO is expected to be transported to the field by end of August 2016.

 