Installation of a Submerged Turret Production Buoy

 

Client: Ocean Installer 
Timeline: 2015 - 2016

Global Maritime's Aberdeen office worked alongside our partners at Vryhof Anchors to deliver a time pressured installation of a Submerged Turret Production Buoy for Ocean Installer.  
The buoy was transported to the field, lifted into the water and connected to to the moorings in the Aje Field offshore Lagos, Nigeria. 

GM was involved in multiple levels of the design, operations and safety considerations throughout the installation.  

Our technical expertise in previous projects was a valuable resource as the project was done in only 8 weeks and would normally be done in 6-8 months