MWS Mafumeira Sul production offshore Angola

 

Client: Chevron
Timeline: 2014 -2016

American Global Maritime provided MWS assurance (2014-2016) for the Phase II field development for Mafumeria Sul project Offshore Angola.

 

The Mafumeira field is located 15 mi (24 km) offshore Cabinda province in block 0. The production facility has a design capacity of 150,000 b/d of liquids and 350 MMcf/d of natural gas. The early production through a temporary production system started in October 2016. Production is ramping up and is expected to continue through 2018.

 

All AGM offices worldwide, participated in the project at one stage or another for the required work:

 

Korea - 5 Modules loaded out in 51 days. This includes deck surveys, installation of around 10 K Mt of grillage, loadout, seafastening & extensive internal seafastening

China – MWS assurance was carried out for loadout, seafastening and sailaway for two platform-platform bridges and for a flare bridge

Mexico (Altamira) – MWS assurance was carried out for loadout, seafastening and sailaway for the accommodation building

Angola – MWS assurance was carried out for loadout, seafastening and sailaway at Port Amboim and Ambriz for 5 jackets and 2 well-head platform topsides

Angola (Offshore) – The offshore MWS campaign provided assurance for the installation of piles, jackets, topside modules, accommodation building, bridges and flare bridges